Lines 2018, 2027, 2028, 2068, 2069, 2721 and 2722 | Construction work in Düdenbüttel: 04.08.2025 - 17.01.2026

From Monday, 04 August 2025 until probably 17 January 2026 the Through road (federal highway 73) in Düdenbüttel under half-sided closure in several construction phases reorganised.

➡️ There are construction site timetables for the construction site - you can find these at here.

On 15 October 2025 begins the third construction phase. The Construction phases 2 and 3 will take place from this date at the same time instead.

The Entry and exit from Heinbockeler Straße onto the Bundesstraße 73 during the work not possible.
➡️ The bus stop „Düdenbüttel, Heinbockeler Straße“ is cancelled. There are replacement stops in both directions set up.

The Lines 2018, 2028, 2068, 2069 and 2721 drive in the direction of Heinbockel Diversion via the crossroads.

The Lines 1824, 2018, 2027, 2028, 2068, 2069, 2721 and 2722 drive in the direction of Stade Diversion via An der Loge, Röthkampstraße and Osterfeldstraße and can also reach the stop „Düdenbüttel, Im Klamm“ cannot be served. An alternative stop has been set up in Osterfeldstraße.